
2027 NA AIDC demand ~35GW vs 16.5–23.4GW supply; power bottleneck locks scarcity and supports pricing.
North American AI data center demand in 2027 runs to roughly 35GW on an IT basis, against 16.5-23.4GW that can actually be delivered. Where our two independent supply methods overlap, that gap is 1.8-2.1x, and it is the number this whole report is built around.
Demand cross-checks two ways and lands in the same place. A CoWoS-capacity build gives 44-49GW of global chip-level power in 2027; a platform-by-platform BOM build gives 48.4GW. The market debates 40-60GW. We assume roughly 50GW globally, with North America taking about two-thirds.
Supply is already locked, and capital cannot move it. The grid path delivers 11-14GW IT, set entirely by who entered the interconnection queue before mid-2025; an application filed today does not make 2027. Behind-the-meter equipment adds 5.5-9.4GW IT net of overlap, but large gas turbine slots are sold out through 2031 on a four-to-five-year order-to-COD cycle, so a frame ordered now becomes supply in 2030-32.
Power delivery is the binding constraint, and it sits upstream of everything a sponsor can pay to accelerate. Permitting killed 78% of the 43GW of stranded projects. Power-side causes explain 60-70% of MW-weighted slippage over the past 12 months. Below that sits licensed labor: a journeyman electrician takes 10,000 hours to train, and only about 30% of MEP workers are in the regions holding 70% of projects. Modular construction compresses the build but not the queue, cutting COD slip probability by only 10-20%.
This report is available to subscribers. Sign in or subscribe to read the full analysis.