CRWVNBISIRENSPCX

Deep|AIDC: 2027 Demand Runs at Roughly 2x Deliverable Supply, and the Binding Constraint Is Power

Wooding, Chen, Ethan, Alicia·August 27, 2026

2027 NA AIDC demand ~35GW vs 16.5–23.4GW supply; power bottleneck locks scarcity and supports pricing.

Executive Summary

North American AI data center demand in 2027 runs to roughly 35GW on an IT basis, against 16.5-23.4GW that can actually be delivered. Where our two independent supply methods overlap, that gap is 1.8-2.1x, and it is the number this whole report is built around.

Demand cross-checks two ways and lands in the same place. A CoWoS-capacity build gives 44-49GW of global chip-level power in 2027; a platform-by-platform BOM build gives 48.4GW. The market debates 40-60GW. We assume roughly 50GW globally, with North America taking about two-thirds.

Supply is already locked, and capital cannot move it. The grid path delivers 11-14GW IT, set entirely by who entered the interconnection queue before mid-2025; an application filed today does not make 2027. Behind-the-meter equipment adds 5.5-9.4GW IT net of overlap, but large gas turbine slots are sold out through 2031 on a four-to-five-year order-to-COD cycle, so a frame ordered now becomes supply in 2030-32.

Power delivery is the binding constraint, and it sits upstream of everything a sponsor can pay to accelerate. Permitting killed 78% of the 43GW of stranded projects. Power-side causes explain 60-70% of MW-weighted slippage over the past 12 months. Below that sits licensed labor: a journeyman electrician takes 10,000 hours to train, and only about 30% of MEP workers are in the regions holding 70% of projects. Modular construction compresses the build but not the queue, cutting COD slip probability by only 10-20%.

Continue reading with FUNDA

This report is available to subscribers. Sign in or subscribe to read the full analysis.